Table 15.

General guideline for using datasets

Subject Descriptions Example
File title The name of each file is listed in the JW-MX-PY (Z) format, where W, X, Y, and Z indicate the number of activities, the number of modes, the number of projects, and the problem number, respectively For example, the file entitled J10-M3-P3 (1) devotes to the first dataset, including 3 projects with 10 activities and 3 execution modes
Contents (sheets) Successor list In the first sheet entitled “Successors List,” the precedence relationships between activities are defined As shown in the Successors List Section of J10-M3-P3 (1), activities 9 and 10 are the successor activities for activity 7 and also, activity 3 is a precedence activity for activities 10 and 11
Duration This sheet expresses the processing time of different modes of activities related to each project As shown in the Duration Section of J10-M3-P3 (1), the processing time of activity 7 in mode 3 for Project 2 is equal to 10
Deadline This sheet belongs to the due dates of completing the projects Based on J10-M3-P3 (1), the due dates of projects 1, 2, and 3 are 24, 22, and 20, respectively
Resource usage This section indicates the number of renewable resources that are required for performing activities of different projects The number of resource type 4 for doing activity 7 in mode 3 for Project 2 is equal to 7 in J10-M3-P3 (1)
Rmax The Rmax Section shows the number of available renewable resources in each project site In J10-M3-P3 (1), there are 16 and 25 units for resource types 2 and 3 in Project site 1
Material usage The Material Usage Section expresses the amount of material needed for performing activities of projects in different modes In J10-M3-P3 (1), 8 and 6 units of material type 1 and 2 are needed to perform activity 7 with mode 2 in Project 3
Ordering cost In this section, the ordering cost of each material type from each supplier is provided As can be seen in J10-M3-P3 (1), the ordering cost of material type 3 from supplier 2 is equal to 10
Holding cost In this sheet, the holding cost of each material type in each period per unit is given The holding cost of material type 3 is equal to 4 in J10-M3-P3 (1)
Penalty-bonus This part includes the bonus/penalty cost due to completing the projects before/after the pre-determined due dates per each period In J10-M3-P3 (1), the bonus and penalty cost for project 3 is equal to 18 and 13, respectively
CF +  The cash inflow of performing activities is provided in this section The cash inflow of activity 7 of Project 2 is 5343
CF −  The cash outflow of performing activities is provided in this section The cash outflow of activity 7 of Project 2 in mode 3 is 68
Lead time In this part, the lead time for purchasing all material type from suppliers for all projects is defined As shown in the Lead Time Section of J10-M3-P3 (1), purchasing material type 2 from supplier 3 for Project 1 is equal to 6
Ir-w This sheet provides the interest rate and importance weight between the average and minimum qualities As shown in J10-M3-P3 (1), the interest rate and the importance weight are 0.064 and 0.37, respectively
Purchase cost This sheet belongs to the unit procurement cost of materials ordered from each supplier with discount policy consideration Based on J10-M3-P3 (1), the purchase cost of material type 1 from supplier 3 is 6 and 3 for the first and second discount ranges, respectively
Discount intervals This section indicates the limitation on discount intervals for all material types related to each supplier The third supplier has two discount intervals for material type 2, [0, 12] and (12, infinity), in J10-M3-P3 (1). In other words, supplier 3 offers a lower price for purchases of more than 12 units
Environmental grades The environmental Grades Section shows the score of each supplier from an environmental perspective In J10-M3-P3 (1), the environmental grade of the second supplier for supplying material types 1 and 2 is 0.726 and 0.557, respectively
Quality The Quality Section expresses the quality of performing activities in different modes In J10-M3-P3 (1), activity 7 in Project 1 can be executed in three modes with quality values 0.973, 0.585, and 0.677