Table 1.
The components of the model.
| Components | |
|---|---|
| Entity | Raw oil |
| Resources | Bascule, Inspectors, PX 60, SRG, SSG, Dryer, Discoloring storage, Operators of odorlessing section, Operators of partitioning section, Operators of hydrogenation section, Operators of filtering section, Operators of post bleach section, and Serak machine |
| Queues | Bascule queue, Laboratory 1 queue, PX60 separator queue, SRG separator queue, SSG queue, Dryer queue, Discolor queue, Odorless queue, Partitioning queue, Hydrogenation queue, Serak machine queue, and Post bleach queue |
| Group Resources | Inspectors, Operators of odorless section, Operators of partitioning section, Operators of hydrogenation, Operators of filtering section, and Operators of post bleach section |
| Transporters | Oil tanker and Liftruck |
| Conveyers | Conveyer |
| Processes | Weighting, Laboratory test, PX60 separator, First washing, Second washing, Drying, Discoloring storages, Odorless, Packaging storages, Serak machine, Packaging, Hydrogenation, Filtering, Post bleach, Cold Storage, and Vacating |
| Scheduling | Regarding to production line that works in three parts of 8 h of a day, scheduling should be done in every section that operators work. Operators who were scheduled are the current operators in group resources |
| Inputs | Entrance of raw oil |
| Outputs | Returning oil, Fatty acid storages, Soup storages, First of neutral line, Solid oil storages, and liquid oil storages |
| Variables | Total oil in process and maximum of oil entrance |