Table 2.
Multivariate logistic regression of the most critical productivity factors.
| The most critical factors | Level | P- Value | AOR | 95% C.I. for Exp (B) |
|
|---|---|---|---|---|---|
| Lower | Upper | ||||
| Limited and low-quality inputs | 0. No 1.Yes | .016 | .116 | .020 | .667 |
| Inappropriate working method & process flow | 0. No 1.Yes | .009 | .059 | .007 | .496 |
| Long lead time | 0. No 1.Yes | .012 | .258 | .051 | 1.31 |
| Less export price of the product | 0. No 1.Yes | .023 | .131 | .023 | .751 |
| Unbalanced workload between workers | 0. No 1.Yes | .018 | .092 | .013 | .666 |
| Poor infrastructure & utility center | 0. No 1.Yes | .002 | .044 | .006 | .314 |
| Human resources & dept. center | 0. No 1.Yes | .010 | .162 | .040 | .651 |
| Quality control department | 0. No 1.Yes | .000 | .061 | .013 | .286 |
| Waiting time | 0. No 1.Yes | .018 | .363 | .156 | .843 |
| Defects | 0. No 1.Yes | .003 | .052 | .008 | .753 |