Table 1.

Maximum times required to generate the dose distribution necessary to perform the quality assurance tasks. The tasks highlighted with (*) have the potential to be automated with dedicated routines handling the data flow between TPS and external software.

(A) Water

Maximum time [min]
(B) Bulk densities

Maximum time [min]
Reference sCT and
(C) Separate NN
Maximum time [min]
(D) dCT

Maximum time [min]
Export MR (*) 2 min
Generate CT DICOM 1 min (*) 30 min
Import DICOM (*) 2 min 2 min
Register CT-MR 5 min
Contour (*) 17.5 min 5 min
Generate ED map (*) 1 min 1 min 1 min 1 min
Calculate dose (*) 1 min 1 min 1 min 1 min
Total 2 min 19.5 min 7 min 44 min