Table 3.
Time distribution by technicians as measured with Form #3.
| Time distribution results | |||||
|---|---|---|---|---|---|
| Activity/Held by | Technician 1 | Technician 2 | Total hours | Activity/Held by | Technician 3 |
| Manufacture of 40 ovitraps | 1 h | 1 h | 2 h | 1st Data transmission | 8 h |
| Installation of 40 ovitraps | 3 h 40 m | 4 h 35 m | 8 h 15 m | 2nd Data transmission | 4 h |
| 1st Reinstallation | 4 h 05 m | 3 h 35 m | 7 h 40 m | 3rd Data transmission | 2 h |
| 2nd Reinstallation | 3 h 45 m | 3 h 30 m | 7 h 15 m | 4th Data transmission | 2 h |
| 3rd Reinstallation | 4 h 08 m | 3 h 45 m | 7 h 53 m | ||
| 4th Reinstallation | 3 h 40 m | 3 h 20 m | 7 h | ||