Pairwise comparison of operational factors.

Operational Factor Location of Project Completion Time Project Risk Facilities of Local Contractor Priorities
Location of Project 1 1 1 9 0,321
Completion Time 1 1 1 9 0,321
Project Risk 1 1 1 9 0,321
Facilities of Local Contractor 0,111 0,111 0,111 1 0,036

CR = 0.