Table 9.
WBS 6 costs in FY$25M
| PERSEUS Mission Estimate (FY25$M) | |||
|---|---|---|---|
| WBS | Description | Total | Notes |
| 6 | Spacecraft | 302.1 | Estimated via parametric models |
| 6.1 | Mechanical | 27.1 | All subsystem estimates use the average of: SEER and PRICE TruePlanning model outputs, as well as APL historical cost per kilogram. FSW and Component Engineering estimates are based on averages from larger APL historical missions. |
| 6.2 | Propulsion | 31.5 | |
| 6.3 | Avionics | 17.1 | |
| 6.4 | Power | 44.1 | |
| 6.5 | Guidance and Control | 15.1 | |
| 6.6 | Thermal | 16.0 | |
| 6.7 | Communications | 40.3 | |
| 6.8 | Harness | 6.2 | |
| 6.9 | Flight Software | 17.0 | |
| 6.A | Component Engineering | 17.7 | |
| 6.X | NG-RTG Mod-1 | 70.0 | Per 2022 Planetary Science and Astrobiology Decadal Study Ground Rules |