Table 5. IQCAMP Project Timeline .

Steps Time (mon)
Design and development
Developing the management and expert teams 2
Developing the other teams including, provincial, IT and analysis 3
Developing sampling method 2
Developing questionnaires 6
Preparing and logistics
Recruiting nurse interviewers 1
Educating interviewers 3
Preparing the materials 2
Conducting the interviews
Recruiting patients 2
Following up 9
Reporting
Cleaning the data 2
Analyzing the data 3
Preparing the reports and articles 14