Table 8.
Data of the 29-activity project.
| No | Logical | Option 1 | Option 2 | Option 3 | ||||||
|---|---|---|---|---|---|---|---|---|---|---|
| T | C | CE | T | C | CE | T | C | CE | ||
| 1 | – | 5 | 2030 | 175.43 | 4 | 2300 | 172.73 | – | – | – |
| 2 | 1FS − 3 days | 8 | 1020 | 106.28 | 7 | 1280 | 93.2 | 6 | 1510 | 86.11 |
| 3 | 1, 2 | 8 | 1700 | 236.25 | 7 | 1850 | 229.24 | 6 | 2090 | 200.88 |
| 4 | 3 | 4 | 590 | 197.92 | 3 | 730 | 193.97 | – | – | – |
| 5 | 4SS + 1 day | 2 | 90 | 140.53 | – | – | – | – | – | – |
| 6 | 1 | 4 | 910 | 117.33 | 3 | 1100 | 115.89 | – | – | – |
| 7 | 2, 6FS − 1 day | 2 | 250 | 112.08 | – | – | – | – | – | – |
| 8 | 7, 3 | 7 | 1490 | 175.52 | 6 | 1650 | 160.49 | 5 | 1830 | 144.46 |
| 9 | 4, 8 | 4 | 520 | 132.87 | 3 | 750 | 119.33 | – | – | – |
| 10 | 5, 9FF + 1 day | 2 | 90 | 87.32 | – | – | – | – | – | – |
| 11 | 5, 10 | 1 | 50 | 92.24 | – | – | – | – | – | – |
| 12 | 11 | 8 | 3260 | 129.99 | 7 | 3580 | 129.61 | 6 | 3710 | 105.67 |
| 13 | 12SS + 2 days | 5 | 1140 | 244.36 | 4 | 1400 | 239.02 | 3 | 1720 | 199.47 |
| 14 | 13SS + 2 days | 4 | 300 | 85.87 | 3 | 450 | 76.27 | – | – | – |
| 15 | 12FS − 4 days,14FS − 2 days | 8 | 1020 | 131.34 | 6 | 1300 | 129.81 | 5 | 1430 | 99.65 |
| 16 | 5FS − 6 days | 9 | 790 | 162.27 | 8 | 900 | 148.99 | 6 | 1180 | 147.82 |
| 17 | 15SS + 4 days | 13 | 3340 | 166.84 | 12 | 3750 | 159.92 | 11 | 4060 | 120.91 |
| 18 | 15FS + 4 days | 9 | 470 | 196.37 | 8 | 650 | 179.28 | 7 | 830 | 172.83 |
| 19 | 15 | 6 | 460 | 201.71 | 5 | 600 | 190.75 | 4 | 810 | 153.89 |
| 20 | 17SS + 3 days | 6 | 1280 | 112.05 | 5 | 1430 | 94.8 | – | – | – |
| 21 | 20SS + 2 days | 14 | 1090 | 218.89 | 12 | 1320 | 204.64 | 10 | 1560 | 167.94 |
| 22 | 21SS + 2 days | 14 | 900 | 180.82 | 11 | 1140 | 178.3 | 9 | 1400 | 172.48 |
| 23 | 22FS − 9 days | 14 | 2220 | 200.77 | 12 | 2510 | 192.33 | 11 | 2690 | 183.89 |
| 24 | 23SS + 6 days | 3 | 230 | 196.33 | – | – | – | – | – | – |
| 25 | 23FS − 4 days | 6 | 1590 | 106.57 | 5 | 1790 | 95.07 | 4 | 1990 | 59.81 |
| 26 | 25SS + 4 days | 10 | 2630 | 93.86 | 9 | 2930 | 82.05 | 8 | 3240 | 49.94 |
| 27 | 26 | 8 | 2060 | 174.75 | 7 | 2450 | 162.6 | 6 | 2660 | 125.81 |
| 28 | 27FS − 3 days | 10 | 320 | 164.01 | 9 | 440 | 153.11 | 8 | 610 | 129.57 |
| 29 | 28 | 1 | 50 | 193.07 | – | – | – | – | – | – |