Skip to main content
. 2024 Jan 2;14:83. doi: 10.1038/s41598-023-50404-w

Table 7.

Direct cost and duration of activity normal and crashing conditions.

Activity Direct cost (LE) Duration (days)
Normal Crash Normal Crash
Piles 15,028,983 19,708,806 40 30
Piles caps 9,221,826 10,069,179 28 20
Piers 6,954,401 7,217,743 19 13
Pier Head 11,645,700 12,596,987 22 17
Beams 27,582,486 27,941,508 46 35
Slabs 20,757,171 22,938,861 56 44
Newgersy and finishing 4,385,353 4,489,881 20 15
Total 95,575,920 104,962,965 145 88