Table 7.
Direct cost and duration of activity normal and crashing conditions.
Activity | Direct cost (LE) | Duration (days) | ||
---|---|---|---|---|
Normal | Crash | Normal | Crash | |
Piles | 15,028,983 | 19,708,806 | 40 | 30 |
Piles caps | 9,221,826 | 10,069,179 | 28 | 20 |
Piers | 6,954,401 | 7,217,743 | 19 | 13 |
Pier Head | 11,645,700 | 12,596,987 | 22 | 17 |
Beams | 27,582,486 | 27,941,508 | 46 | 35 |
Slabs | 20,757,171 | 22,938,861 | 56 | 44 |
Newgersy and finishing | 4,385,353 | 4,489,881 | 20 | 15 |
Total | 95,575,920 | 104,962,965 | 145 | 88 |