Table 1.

Evaluation table of lean model improvement.

Process efficiency Productivity (m2/work) Construction cycle time (h) Labor cost (VND)
Real world model 0.136 3.53 107.83 182 million
Lean model 0.501 8.52 93.8 72.4 million
Improvement 268% 141% 13% 96%