Table 5. Estimation of time needed to execute the following scenarios.
| Scenario | Estimated time using an ETL tool | Estimated time using ETLCL |
|---|---|---|
| 1. (a) | 8 man-hours | 1 man-hour |
| 1. (b) | 16 man-hours | 2 man-hours |
| 1. (c) | 16 man-hours | 2 man-hours |
| 1. (d) | This scenario is not usually supported by ETL tools | Performed by the engine for an very short amount of time |
| 1. (e) | On demand—it depends on the operation team | 10 man—minutes |
| 1. (f) | 1 man-hour | 10 man—minutes |
| 2. | No more than two man-days | No more than 2 man-hours |
| 3. | N/A | No more than 3 man-hours |