Two-level RBS decomposition of lifting operation process.

Man risk: R1 Machine risk: R2 Material risk: R3 Method risk: R4 Environment risk: R5
Low safety awareness: R11 Equipment out of the factory with disease: R21 Poor quality of the suspension: R31 Improper investigation of safety hazards: R41 Extreme weather conditions: R31
Wildcat operatio: R12 Balance of plant fault: R22 Poor quality of spreader: R32 Improper safety education and training: R42 Cross operation: R32
Unlicensed employment: R13 Improper maintenance: R23 There is no full-time supervisor on site: R43 Poor hydrogeological conditions: R33
Improper use of safety protective equipment: R14 Limiter failure: R24 Improper special construction scheme: R44 Lack of on-site warning signs: R34
Violate commanding: R15 Improper equipment layout: R25 Improper disclosure of construction technology: R45
Physical discomfort on duty: R16
Risk Operation: R17