. 1999 Jul 3;319(7201):48–51. doi: 10.1136/bmj.319.7201.48

Table 4.

Capital costs and annual payments of private finance initiative (PFI) hospitals

NHS trust Annual income 1996-7 (£m) Current asset base 1996-7 (£m) PFI construction costs (£m) 1996-7 annual capital costs* (£m) PFI availability payment (£m) Availability fee as % of income Availability fee as % of construction costs
Calderdale 72.7 35.2 64.6 4.7 9.0 12.4 13.5
Carlisle Hospitals 46.3 19.6 64.7 2.7 8.0 17.3 12.4
Greenwich 95.2 55.0 84.0 8.7 11.0 11.5 13.1
Norfolk and Norwich 122.1 19.0 143.5 12.7 15.6 12.8 15.5
North Durham 59.0 24.9 61.0 3.6 7.1 12.0 11.6
Wellhouse 83.6 105.0 54.0 5.2 10.0 12.0 18.5
*

Interest, dividends, depreciation, rental.