Table 13.

Present and Suggested Roads’ transportation time calculations.

Crew description Unit Number of crews Production rate Present road quantities Suggested road quantities Present road’s duration in “hrs” Suggested road’s duration in “hrs”
2 Loader + 2*50 m3 Dump Trucks " for loading and unloading excavated materials to public dumpster" m3/day 1 471.5 399,795 177,950 6783.2 3019.2
1 Loader + 2*50 m3 Dump Trucks " for loading Replacement Soil from quarry to site" m3/day 1 381.6 348,180 21,750 7300.2 456.0
1 Loader + 2*50 m3 Dump Trucks " for loading Coarse Aggregate from Ataqa mine to site" m3/day 1 154.9 24,336 28,808 1256.5 1487.5
1 Asphalt Batch Plant + 8*20 m3 Dump Trucks m3/day 1 200 6,739 7,978 269.6 319.1
2 Loader + 8*20 m3 Dump Trucks “for loading and unloading materials within the site boundaries” m3/day 1 1000 372,516 50,558 2980.1 404.5