Table 3.

Estimated duration of work phases in the ground-based and drone-based survey methods, expressed as mean ± standard deviation (SD), n = 12. System time refers to automated steps and does not involve human labor.

Work phase Ground survey Drone survey
Field operations Field preparations ~ 1 h ~ 1 h
Field survey 1 h 58 min ± 47 min 8 min ± 4 min
Drone image processing Align photos (automated) 1 h 17 min ± 55 min
Build dense cloud (automated) 23 h 4 min ± 17 h 27 min
Build Tiled Model (automated) 20 min ± 15 min
Build DEM (automated) 1 min ± 1 min
Build Orthomosaic (automated) 8 min ± 5 min
Data processing Spatial digitization of shoots 25 min ±8 min 14 min ± 7 min
Shoot spatial analysis ~ 10 min ~ 10 min
Total human work time ~ 3 h 30 min ± 55 min ~ 1 h 30 min ± 10 min
Total system time (inc. processing) ~ 1 h ~~24 h 50 min ± 18 h 43 min (23 h automated)