Table 1.

Summary of the core components of the Smart Hospital Initiative.

PROJECT PHASE COMPONENT SPECIFIC ACTIVITIES TIMELINE
1 Assessments HSI status for safety, development of Green Checklist to establish the level of greening 2009/2014 Pre- and post- retrofitting
1 Retrofitting Design and construction of improvements to infrastructure 2009–2014
2 Assessments HSI and Green Checklist for status in terms of safety and greenness 2015–2017 depending on country
2 Site selection Cost-effectiveness analysis study of proposed retrofits based on the contribution of safety and greening works 2016–2017 depending on country
2 Training Preparatory training for constructors and for staff to enhance familiarity with new systems; emergency planning skills 2016–2018
2 Retrofitting Design, tendering and construction 2017–2023, interrupted by Hurricane Maria and COVID-19
2 Training Focus on maintenance and care of installations 2019–2022
2 Surveys and evaluation Impact of the project 2020–2023
2 Outreach Sharing of best practices 2022 onwards