Table 1.
Summary of the core components of the Smart Hospital Initiative.
| PROJECT PHASE | COMPONENT | SPECIFIC ACTIVITIES | TIMELINE |
|---|---|---|---|
| 1 | Assessments | HSI status for safety, development of Green Checklist to establish the level of greening | 2009/2014 Pre- and post- retrofitting |
| 1 | Retrofitting | Design and construction of improvements to infrastructure | 2009–2014 |
| 2 | Assessments | HSI and Green Checklist for status in terms of safety and greenness | 2015–2017 depending on country |
| 2 | Site selection | Cost-effectiveness analysis study of proposed retrofits based on the contribution of safety and greening works | 2016–2017 depending on country |
| 2 | Training | Preparatory training for constructors and for staff to enhance familiarity with new systems; emergency planning skills | 2016–2018 |
| 2 | Retrofitting | Design, tendering and construction | 2017–2023, interrupted by Hurricane Maria and COVID-19 |
| 2 | Training | Focus on maintenance and care of installations | 2019–2022 |
| 2 | Surveys and evaluation | Impact of the project | 2020–2023 |
| 2 | Outreach | Sharing of best practices | 2022 onwards |