Table 2. Main difference aspects between long-term and short-term mine planning.

Aspects Long-term mine plan Short-term Mine plan
Discretization of time Quarterly to yearly often for medium-term or more for long-term, Shift-to-shift, daily, weekly, monthly
Block model Millions of equally sized blocks according the grade (High grade, low grade, waste) for different destination (Plant, stockpile and waste dump) respectively Set or portions of blocks with irregularly shaped according the grade (High grade, low grade, waste) for different destination (Plant, stockpile and waste dump) respectively
Geotechnical Global pit stability with a safe and optimal overall angle, and pit monitoring Bench face angle stable and suitable mining operations
Design Global pit design and pushback respecting pit slope (overall angle) Pushbacks designs, available mining faces,
Mining precedence’s Blocks directly above to be extracted before a block below according to the pit slope angle Accessing blocks from the mining faces
Cost Maximization of Net Present Value (NPV) Maximizing equipment utilization and minimizing costs or losses (Rehandling …)
Equipment’s Fleet size available (Number of Trucks and loading equipment) Modelling of individual of equipment available (Drill rigs, shovels and trucks …