Introduction |
Designation of national focal point |
To spearhead IVM |
October 2004 |
|
Training of national focal point |
To develop the National Action Plan |
November 2004 |
|
National steering committee constituted |
To review and adopt WHO guidelines for VCNA |
February 2005 |
|
Vector Control Needs Assessment |
To determine gaps in policies, legislation and capacity |
May 2005 |
|
National Stakeholders Consensus Workshop |
To adopt VCNA report and endorse IVM as national strategy |
June 2005 |
|
Draft country specific IVM guidelines produced |
To adapt strategies to local conditions |
2005 |
|
Capacity building workshops on IVM conducted |
To train provincial and district personnel |
2005 |
|
National Entomology laboratory upgraded |
To enhance evidence-based decision-making |
2005 |
|
Five district selected to conduct epidemiological assessments and develop district action plan |
To operationalize IVM (IRS, ITNs, Larviciding and E. management). |
2005 |
Consolidation |
Quarterly national IVM committee meetings conducted |
To ascertain functionality of IVM structures |
Every quarter |
|
Yearly review of the national action plan |
To incorporate and address policy and regulatory issues |
Yearly |
|
Conduct trainers of trainers workshops |
To strengthen capacity for vector control |
Yearly |
Expansion |
IVM training workshop conducted |
To scale up interventions to 19 districts |
November 2006 |