Time from migration decision to database specifications received |
0.6 |
0.3–1.0 |
Time from database specifications received to data entry system ready |
3.5 |
1.6–8.5 |
Time from data entry system ready to data validation checks ready |
1.9 |
0–3.5 |
Time from data validation checks ready to reports ready |
4.2 |
2.5–7.0 |
Total duration of system development |
8.5 |
3.0–15.5 |
Months without reports |
8.1 |
5.6–11.4 |
Time from database specifications received to all data received |
3.6 |
2.3–4.6 |
Time from migrated data received to all migrated data entered |
3.8 |
3.0–5.1 |
Time from last patient last visit to database lock |
2.8 |
2.3–3.3 |