Table 1.

Calendar of selected events

Date Event
2000-2003 Discussion with peers regarding details of trial design
2004 Initial submission to NINDS and CIHR
Sept 2004 Publication of protocol, version 1 (11)
Feb 2006 Conditional approval by CIHR
Feb-Jun 2006 DSMC Charter
Jun 2006 Official approval for a third of support
Sept 2006 Full financial support
Application to IRBs for trial initiation
May 2007 Approval for French Centres
June 2008 Approval for UK Centres
July 2008 Publication of final protocol in Trials (10)
Sept 2008 Letter of progress to CIHR
Application to NINDS for US Centres
Oct 31st 2008 Unilateral trial interruption ordered by CIHR
November 6th 2008 First International investigator meeting
June 2009 Trial Interruption by Steering Committee
2010-2011 Preparation and publication of final report