number of first- and second-year projects

Year 1 Year 2 Hospital wide
Project Projects Mean Range Projects Mean Range Year 1 Year 2
Pressure ulcers 20 2.5 2-5 55 6.9 0-20 1 3
Medication safety 17 2.3 1-4 95 11.9 0-23 3a
Operating theatre 8 1.0 0-0 5 0.6 0-2
Postoperative wound infections 10 1.3 1-2 30 3.8 1-13 1
Process redesign 26 3.3 1-5 55 6.9 2-16 2
Working without waiting lists 26 3.3 1-5 57 7.1 3-14
Total 107 2.3 1-5 297 6.2 0-23 1 9

aFour medication safety projects were disseminated hospital-wide, but only three cases happened during the multilevel quality collaborative. Unnecessary intravenous antibiotics was spread in two hospitals; in one of them in the second year, in the other before the programme. Unnecessary blood transfusions was spread in the second year in two hospitals.