Table 7.
Health system-wide cost calculation (cord blood) using various approaches
Cum. | PPU (USD) | Total (USD) | PPP (USD) | Total (USD) | PPP2 (USD) | |
---|---|---|---|---|---|---|
Sirchia “A” | ||||||
CBU available | 537,000 | 11,602 | 6,230,274,000 | 6,230,274,000 | ||
CBU provided | 21,387 | 27,579 | 589,832,073 | 589,832,073 | ||
Total | 3.98% | 6,820,106,073 | 318,890 | 5,640,441,927 | 263,732 | |
Sirchia “B” | ||||||
CBU available | 537,000 | 46,408 | 24,921,096,000 | 24,921,096,000 | ||
CBU provided | 21,387 | 27,579 | 589,832,073 | 589,832,073 | ||
Total | 3.98% | 25,510,928,073 | 1,192,824 | 24,331,263,927 | 1,137,666 | |
Howard “A” | ||||||
CBU available | 537,000 | 31,107 | 16,704,459,000 | 16,704,459,000 | ||
CBU provided | 21,387 | 27,579 | 589,832,073 | 589,832,073 | ||
Total | 3.98% | 17,294,291,073 | 808,636 | 16,114,626,927 | 753,478 | |
Howard “B” | ||||||
CBU available | 537,000 | 29,568 | 15,878,016,000 | 15,878,016,000 | ||
CBU provided | 21,387 | 27,579 | 589,832,073 | 589,832,073 | ||
Total | 3.98% | 16,467,848,073 | 769,993 | 15,288,183,927 | 714,835 |
Notes: Calculations based on the publications of Sirchia et al7 and Howard et al.8 For each publication, an optimistic approach (“A”) and a realistic approach (“B”) was defined.
Abbreviations: Cum, cumulative; PPU, price-per-unit; PPP, price-per-product (system based approach); PPP2, price-per-product (institution-based approach).