TABLE I.

Timelines and key milestones of the surgical synoptic reporting tool implementation in Nova Scotia

Timeline Milestone
Apr–May 2008 Kick-off meeting for project, with Alberta surgical synoptic reporting team and Nova Scotia partners
National meeting in Montreal, QC, with key decision-makers from participating provinces
May–Nov 2008 Development of project plan
Engagement of partners through small-group meetings
Establishment of 3 working groups [information technology (it), quality/information management, privacy]
Feb–Dec 2009 it “gap” analysis with visiting software vendor
Funding delays
Completion of privacy impact assessment and threat risk assessment
Formal request for funding proposals to conduct the it work identified by the gap analysis
Hiring of part-time it lead (October)
Work to integrate provincial it systems starts by end of year
Jan–Jun 2010 Continuation of it integration work
Intensive change-management focus as project nears “go-live” date
Jul–Aug 2010 System goes “live” (July)
Training and initiation of a small number of surgeons
Testing period and resolution of identified issues
Sep–Dec 2010 Training of all surgeons, initial adoption, and use
Consensus on national data standards for surgical reportinga
a

Adaptation or customization of disease site templates and work toward establishment of national data standards occurred throughout the first 2 years of the project.