Skip to main content
. 2012 Dec 23;2012:450685. doi: 10.1100/2012/450685

Table 9.

Component decision tree for impacts on benthic habitat and resources. The key is followed to obtain a recommended suite of monitoring protocols.

Determine which impacts to the benthic environment need to be monitored:
The energy resource is
Wind Go to A
Waves Go to B
Tidal Go to C
(A) The wind turbine foundation is
Monopile OR tripod OR lattice Go to A1
Gravity Go to A2
Floating mooring Go to A3
 (A1) The stage of the monopile, tripod, or lattice wind turbine project is
 Construction Z1, Z2
 Operation Z1, Z2, Z3
 Decommissioning Z1, Z2
 (A2) The stage of the gravity wind turbine project is
 Construction Z1, Z2, Z3
 Operation Z1, Z2, Z3
 Decommissioning Z1, Z2, Z3
 (A3) The stage of the floating mooring wind project is
 Construction Z1, Z2
 Operation Z1, Z2
 Decommissioning Z1, Z2
(B) The tidal turbine type is
Open OR shrouded bottom mounted Go to B1
Open OR shrouded floating mooring Go to B2
 (B1) The stage of the bottom-mounted tidal turbine project is
 Construction Z1, Z2
 Operation Z1, Z2, Z3, Z4
 Decommissioning Z1, Z2
 (B2) The stage of the floating mooring tidal turbine project is
 Construction Z1, Z2
 Operation Z1, Z2, Z4
 Decommissioning Z1, Z2
(C) The wave device type is
Point absorber OR wave attenuator OR oscillating water column Go to C1
Oscillating wave surge converter Go to C2
Overtopping Go to C3
 (C1) The stage of the point absorber OR wave attenuator OR oscillating water column project is
 Construction Z1, Z2
 Operation Z2, Z4
 Decommissioning Z1, Z2
 (C2) The oscillating wave surge converter project scale is
 Construction Z1, Z2
 Operation Z1, Z2, Z3, Z4
 Decommissioning Z1, Z2
 (C3) The overtopping device project scale is
 Construction Z1, Z2
 Operation Z1, Z2, Z4
 Decommissioning Z1, Z2

Recommended protocols:

Z1: seabed scour and/or deposition.

Z2: changes in benthic community composition.

Z3: increase in hard bottom habitat.

Z4: changes in hydrodynamics.