a. Environmental Improvement | |||
| |||
---|---|---|---|
Strategy area | Not Discussed, % | Discussed/Planned, % | In-Progress/Completed, % |
| |||
Transit and parking | 59 | 15 | 24 |
Infill and redevelopment | 71 | 5 | 19 |
Children’s play areas | 49 | 17 | 32 |
Street improvements | 31 | 27 | 41 |
Safe Routes to School | 15 | 22 | 51 |
Public plazas | 32 | 8 | 56 |
Streetscaping | 22 | 19 | 56 |
Parks and recreation | 14 | 17 | 63 |
| |||
b. Policy Change | |||
| |||
Strategy area | No New Policy, % | Policy Gap Identified/Discussion Initiated, % | Policy Drafted/Adopted, % |
| |||
Transit and parking | 78 | 3 | 19 |
Infill and redevelopment | 78 | 7 | 15 |
Children’s play areas | 75 | 13 | 12 |
Street improvements | 46 | 17 | 37 |
Safe Routes to School | 46 | 24 | 31 |
Public plazas | 58 | 12 | 31 |
Streetscaping | 46 | 12 | 42 |
Parks and recreation | 46 | 12 | 42 |