Table 2.

The detailed segment composition of building construction progress.

Construction progress
First-order progress influence factor segments Second-order progress influence factor segments Progress score value
Site leveling progress (T 1) Scene investigation progress (T 11) R 11
Removing obstacle progress (T 12) R 12
Calibrating range, setting benchmarks, and grid progress (T 13) R 13
Measuring elevation progress (T 14) R 14
Calculating earthwork cut and fill engineering quantities progress (T 15) R 15
Land leveling progress (T 16) R 16
Field compaction progress (T 17) R 17

Ground foundation progress (T 2) Earth excavation progress (T 21) R 21
Cushion placement progress (T 22) R 22
Foundation placement progress (T 23) R 23
Foundation wall placement progress (T 24) R 24
Base pillar, ground ring beam progress (T 25) R 25
Backfilling earthwork progress (T 26) R 26

Body engineering progress (T 3) Reinforcement engineering progress (T 31) R 31
Formwork engineering progress (T 32) R 32
Concrete engineering progress (T 33) R 33
Masonry engineering progress (T 34) R 34

Roof engineering progress (T 4) Clean up, leveling progress (T 41) R 41
Processing insulation layer progress (T 42) R 42
Waterproofing and drainage progress (T 43) R 43
Setting qualified seaming progress (T 44) R 44
Ventilation, exhaust progress (T 45) R 45

Decoration and fitment progress (T 5) Groundwater seepage test of bathroom and kitchen progress (T 51) R 51
Laying chisel trough and circuit pipeline progress (T 52) R 52
Sealing and burying trunk progress (T 53) R 53
Decoration and fitment progress of public wall (T 54) R 54
Installing doors and windows progress (T 55) R 55

Water, electricity, and HVAC progress (T 6) Water supply and sewerage progress (T 61) R 61
Laying circuit progress (T 62) R 62
Installing heating progress (T 63) R 63
Water, heating, and electrical test progress (T 64) R 64

Equipment installation progress (T 7) Installing elevator progress (T 71) R 71
Installing fire-fighting equipment progress (T 72) R 72
Installing emergency device progress (T 73) R 73

Goods transportation progress (T 8) Goods transportation scheme 1 progress (T 81) R 81
Goods transportation scheme 2 progress (T 82) R 82
Goods transportation scheme 3 progress (T 83) R 83

Environmental factor progress (T 9) Natural environment factor progress (T 91) R 91
Social environment factor progress (T 92) R 92

Other factors progress (T 10) Construction design drawings change progress (T 101) R 101
Construction machinery, materials changes progress (T 102) R 102
Progress affected by weak supervision (T 103) R 103
Progress affected by supply failure of the municipal system (T 104) R 104
Progress affected by great political and social activities (T 105) R 105