Table 2.

Fourteen experts’ estimates of construction duration in months for each of the single-unit plants

Expert 1,000-MWe Gen III+ LWR plant 45-MWe SMR plant 225-MWe SMR plant
A 72 36 48
B 42 18 24
D 60 42 30
E 60 36 48
F 60 36 36
G 72 36 48
H 48 36 36
I 60 24 30
J 66 54 48
K 54 30 36
L 54 36 36
N 60 24 36
O 48 36 36
P 48 24 36
Mean 57 33 38

Construction duration was defined as the period from the pouring of first safety concrete to plant commissioning and delivery of the first kilowatt-hour. Experts C and M did not respond to this question.