Table 1.

Timeline for the development and deployment of our solution in the nursing home (14 months trial)

Timeline Description Activities
Mar 2010 - Mar 2011
Observations, discussions & prototyping
Pre-deployment
Apr - June 2011
Prototyping & Demo
 
Jul 2011
Application for ethics approval
 
Aug 2011
Ethics approval obtained
 
Aug - Oct 2011
Initial trial setup and field testing of system
 
Oct - Jan 2012
First phase (1 room, 4 months trial)
Deployment
Jan - Feb 2012
Analysis, features update & performance tuning
+
Feb - May 2012
Second phase (1 room, 4 months trial)
Ground truth
May - June 2012
Analysis & questionnaire survey
+
June - Nov 2012
Third phase (3 rooms, 6 months trial)
Data analysis
Nov - Dec 2012 Analysis & questionnaire survey