Capital cost factors for rBuChE case study.

Capital cost factors
Estimated based on PC (listed equipment PC plus unlisted equipment PC)
Unlisted equipment 0.2 listed purchased equipment cost

Direct costs Plant growth Agroproduction/infiltration rBuChE recovery/purification

Piping 0.1 PC 0.35 PC 0.35 PC
Instrumentation 0.2 PC 0.4 PC 0.4 PC
Insulation 0.01 PC 0.03 PC 0.03 PC
Electrical facilities 0.1 PC 0.1 PC 0.1 PC
Building 0.2 PC 0.45 PC 3 PC
Yard improvement 0.15 PC 0.15 PC 0.15 PC
Auxiliary facilities 0.1 PC 0.4 PC 0.4 PC
UE installation 0.5 UEPC 0.5 UEPC 0.5 UEPC
Direct costs multiplicative factor 2.35 2.88 5.43
Engineering 0.25 DC 0.25 DC 0.25 DC
Construction 0.35 DC 0.35 DC 0.35 DC
Indirect costs multiplicative factor 1.41 1.73 3.26
Contractors fee 0.05 DC + IC 0.05 DC + IC 0.05 DC + IC
Contingency 0.1 DC + IC 0.1 DC + IC 0.1 DC + IC
Other costs multiplicative factors for DFC 0.56 0.69 1.30
Total multiplicative factor for DFC 4.33 5.30 9.99
Total multiplicative factor for TCI (except working capital) 4.54 5.56 10.49

PC: purchase cost; DC: direct cost; IC: indirect cost; UEPC: unlisted equipment purchase cost; DFC: direct fixed capital; TCI: total capital investment.