1. Owner related |
1.1 Slow decision making |
1.2 Suspension of work |
1.3 Late in revising and approving design documents by owner |
1.4 Delay to furnish and deliver the site to the contractor |
1.5 Delay in finance and payments of completed work by owner |
1.6 Variation orders/changes of scope by owner during construction |
1.7 Type of project bidding and award (negotiation, lowest bidder) |
1.8 Unrealistic contract duration |
1.9 Ineffective delay penalties |
1.10 Owner interference |
|
2. Consultant related |
2.1 Inadequate experience of consultant |
2.2 Delay in approving shop drawings and sample materials |
2.3 Mistakes and discrepancies in design documents |
2.4 Unclear and inadequate details in drawings |
2.5 Quality assurance/control |
|
3. Contractor related |
3.1 Difficulties in financing project by contractor |
3.2 Poor site management and supervision |
3.3 Ineffective planning and scheduling of project |
3.4 Rework due to errors during construction |
3.5 Delays in sub-contractors work |
3.6 Inadequate contractor experience |
3.7 Delay in site mobilization |
3.8 Delay in preparation of shop drawings and material samples |
|
4. Material related |
4.1 Shortage of construction materials in market |
4.2 Delay in material delivery |
4.3 Changes in material types and specifications during construction |
|
5. Labor & equipment related |
5.1 Shortage of labors |
5.2 Unqualified workforce |
5.3 Low productivity level of labors |
5.4 Equipment availability and failure |
|
6. Project related |
6.1 Effects of subsurface conditions (e.g., soil, high water table, etc.) |
6.2 Traffic control and restriction at job site |
6.3 Unavailability of utilities in site or Delay in providing services from utilities such as (water, etc.) |
6.4 Accident during construction |
6.5 Problem with neighbors |
|
7. External related |
7.1 Weather effect (hot, rain, etc.) |
7.2 Environmental restrictions |
7.3 Changes in government regulations and laws |
7.4 Slow permit by government/municipality |
7.5 Delay in performing final inspection and certification by a third party |
7.6 Lack of communication between the parties |
7.7 Fluctuations in cost/ currency |
7.8 Force Majeure as war, revolution, riot, strike, and earthquake, etc. |