Delay causes of construction projects.

Delay group Causes
1. Owner related 1.1 Slow decision making
1.2 Suspension of work
1.3 Late in revising and approving design documents by owner
1.4 Delay to furnish and deliver the site to the contractor
1.5 Delay in finance and payments of completed work by owner
1.6 Variation orders/changes of scope by owner during construction
1.7 Type of project bidding and award (negotiation, lowest bidder)
1.8 Unrealistic contract duration
1.9 Ineffective delay penalties
1.10 Owner interference



2. Consultant related 2.1 Inadequate experience of consultant
2.2 Delay in approving shop drawings and sample materials
2.3 Mistakes and discrepancies in design documents
2.4 Unclear and inadequate details in drawings
2.5 Quality assurance/control



3. Contractor related 3.1 Difficulties in financing project by contractor
3.2 Poor site management and supervision
3.3 Ineffective planning and scheduling of project
3.4 Rework due to errors during construction
3.5 Delays in sub-contractors work
3.6 Inadequate contractor experience
3.7 Delay in site mobilization
3.8 Delay in preparation of shop drawings and material samples



4. Material related 4.1 Shortage of construction materials in market
4.2 Delay in material delivery
4.3 Changes in material types and specifications during construction



5. Labor & equipment related 5.1 Shortage of labors
5.2 Unqualified workforce
5.3 Low productivity level of labors
5.4 Equipment availability and failure



6. Project related 6.1 Effects of subsurface conditions (e.g., soil, high water table, etc.)
6.2 Traffic control and restriction at job site
6.3 Unavailability of utilities in site or Delay in providing services from utilities such as (water, etc.)
6.4 Accident during construction
6.5 Problem with neighbors



7. External related 7.1 Weather effect (hot, rain, etc.)
7.2 Environmental restrictions
7.3 Changes in government regulations and laws
7.4 Slow permit by government/municipality
7.5 Delay in performing final inspection and certification by a third party
7.6 Lack of communication between the parties
7.7 Fluctuations in cost/ currency
7.8 Force Majeure as war, revolution, riot, strike, and earthquake, etc.