Owner related |
1.7 Type of project bidding and award (negotiation, lowest bidder) |
68.94 |
Contractor related |
3.3 Ineffective planning and scheduling of project |
68.94 |
Owner related |
1.6 Variation orders/changes of scope by owner during construction |
66.67 |
Owner related |
1.3 Late in revising and approving design documents by owner |
65.15 |
Owner related |
1.5 Finance and payments of completed work by owner |
64.39 |
Contractor related |
3.2 Poor site management and supervision |
64.39 |
Labor & equipment |
5.3 Low productivity level of labors |
64.39 |
Contractor related |
3.1 Difficulties in financing project by contractor |
63.64 |
Project related |
6.1 Effects of subsurface conditions (e.g., soil, high water table, etc.) |
62.12 |
Owner related |
1.1 Slow decision making |
57.58 |