Table 5.

Median and range of frequency for delay causes groups.

Delay causes group Owner respondents Consultant respondents Contractor respondents P value
Owner related 21(12–31) 24(11–28) 24(15–31) 0.369
Consultant related 6(5–11)a 7(5–10)a 10(6–13)b 0.024
Contractor related 18(12–24)a 17(12–23)a 15(8–19)b 0.059
Material related 5(3–7) 5(3–7) 4(3–7) 0.925
Labor & equipment related 8(5–10) 8(5–11) 7(4–11) 0.368
Project related 9(5–11) 10(6–12) 9(5–14) 0.891
External related 13(9–18) 12(8–17) 12(8–20) 0.764
Total 80(51–112) 83(50–108) 81(49–115) 0.966

Notes: The respondents group which has a different superscript b is significantly different from the other two respondents groups which have superscript a (e.g. Causes group 2).