Skip to main content
. 2015 May 11;8:10.3402/gha.v8.26494. doi: 10.3402/gha.v8.26494

Table 3.

Estimated weekly time spent on recruitment and management of agency nursesa

Indirect cost element Hospital 1 Hospital 2
Pre-employment checks Not done Not done
Identify need for agency nurses 1 4
Arranging cover/recruitment of agency nurses 10.5 20
Orientation 2 8
Supervision, including dealing or managing problems 28 20
Verification of invoices 0 4
Processing of invoices 10b 4
Processing of payments Done centrally Done centrally
Monitoring of expenditure Not done Not done
Total hours per week 51.5 60
Estimated indirect cost per week 962,267 300,121
a

In calculating hours per week, it was assumed that managers worked 8 hours per day and 5 days per week.

b

Hospital 1 spent 4 hours per agency per invoice every 2 weeks. There were five agencies, averaging 10 hours per week.