Table 1.
Activity | March 2013 | April 2013 | May 2013 | June 2013 | July 2013 | August 2013 | September 2013 | October 2013 | November 2013 | December 2013 | January 2014 | February 2014 | March 2014 |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Identifying stakeholders | |||||||||||||
Pre-intervention workshops | |||||||||||||
Formation of core group in each cluster | |||||||||||||
Interventions in community | |||||||||||||
Process evaluation |
Gray shades indicate the time period during which the activity took place.