Timeline for the SAMBA project. *Dark cells represent intervention periods, and blank cells represent control periods. The inclusion of patients will start on January 15th 2015 and end on June 15th 2016. The last six month follow-up will be in December 2016 and the last 12-month follow-up will be in June 2017. #The 6 municipalities will switch from control phase to intervention phase in a randomized order