Month/Year of CPOE launch and achievement of facility use rate of 80%

Facility Month/Year CPOE Launch Month/Year 80% CPOE Use Rate Months Required to Achieve 80%+ CPOE Use Level
CSR-Westover Hills March 2012 February 2013 11
CSR-New Braunfels May 2012 May 2014 24
CSR-Medical Center August 2012 February 2014 18
CSR-Children’s Hospital of San Antonio November 2014 January 2015 2