Skip to main content
. 2017 Jun 12;17:399. doi: 10.1186/s12913-017-2347-4

Table 4.

Average potential savings from efficiency by facility characteristics

Variable Mean (GH₵) Standard Error
Facility location
 Rural 7528.61 841.93
 Urban 19,647.16 5271.72
Facility Type
 Private 38,395.9 8499.89
 Public 9600.114 1484.612
Administrative region
 Ashanti 19,114.26 6556.09
 Brong Ahafo 5714.15 4958.34
 Central 25,737.83 10,556.45
 Eastern 7763.96 1473.81
 Greater Accra 6559.77 2754.89
 Northern 8591.75 3815.11
 Upper East 11,834.81 2530.16
 Upper West 8448.45 3159.05
 Volta 5007.98 1461.34
 Western 5552.22 1910.23
Performance Based Financing
 No 10,088.67 1656.78
 Yes 25,312.6 17,148.66
Mean 10,593.07 14,548.3

Source: Authors’ computation

Average exchange rate in 2011 was US$1.00 = GH₵1.50