Table 2.
Pre-core-lab | Core-lab | |
---|---|---|
Direct costs, € | ||
Equipment | 14,950.00 | 20,450.00 |
Staff | 352,898.86 | 301,217.78 |
Total | 367,848.86 | 321,667.78 |
Indirect costs (4.61% of direct costs), € | 16,954.05 | 14,825.82 |
General costs (13.95% of direct +indirect costs), € | 53,680.01 | 46,940.82 |
Total, € | 438,482.91 | 383,434.18 |