Skip to main content
. 2017 Jun 2;33(4):854–866. doi: 10.1002/btpr.2492

Table 6.

E‐factor Scores for the Alternative Batch, Continuous and Hybrid Manufacturing Strategies

Manufacturing Strategies Water (kg/kg product) Consumable (kg/kg product)
Base case 3,900–7,250 6–73
FB‐CB 3,000–6,400 8–61
ATF‐CB 2,150–5,500 6–35
FB‐CC 2,750–7,450 13–48
ATF‐CC 2,300–5,550 8–25