Example of laboratory action plan derived from the summary of assessment findings.

Action item Responsible persons Timeline Signature Review after due date
Review 1 Review 2 Review 3
QA Officer to review document control header QA Officer 30 June

The person assigned the task has to sign as an indication of responsibility of the task. After each due date, the progress of the action item is reviewed and status updated under review 1 to 3.