The first-of-a-kind process was never piloted |
Pilot the process and use pilot data to design and build the large-scale plant |
Performance unexpectedly deviated at scale and target metrics were not achieved |
Use large-scale models to identify critical scale-up parameters and evaluate them in lab/pilot scale-down tests as early and often as possible |
The engineering and construction teams had never designed or built a similar plant before |
Use an engineering design, procurement and construction team that has worked on a similar project before |
Industrial grade raw materials were never validated ahead of scale-up |
Validate all industrial raw materials in lab/pilot studies ahead of procurement |
The operations team wasn’t trained prior to plant start-up |
Give your operations team training and operating experience in the pilot plant |
Plant utilities were unreliable |
Engineer in utility redundancy where feasible and validate utilities ahead of start-up; understand how utility interruptions will impact your process |
There were no systems in place to properly transfer technology or troubleshoot process deviations |
Install lab-scale fermentors in the plant lab to facilitate technology transfer and process troubleshooting |
Sterility validation of fermentation systems was skipped |
Perform a rigorous sterility validation program that assesses the entire sterile boundary |
Critical equipment or instrumentation was eliminated to cut cost |
Identify and install equipment/instruments that are critical for process monitoring and control |
The operations team did not know how to respond to process upsets, resulting in lost batches/product |
Perform rigorous process upset testing at lab/pilot scale and develop a detailed upset response plan; train the operations team both in the pilot plant and by using process simulators |
There was no preventive maintenance program in place; equipment losses resulted in significant production delays |
Put in a place a preventive maintenance program and hire skilled maintenance engineers; identify critical process equipment (e.g. valves, pumps) and keep back-ups on-site |
Poor project management resulted in significant delays |
Assign a skilled, dedicated project manager to coordinate and oversee activities |
Business and technical management imposed unrealistic constraints on project cost and schedule |
Resist pressures to overpromise; stress test plans with domain experts; identify and weigh project execution risks against rewards and penalties |
There wasn’t enough money available to run the plant once it was built |
Reserve enough time to properly commission and start-up the plant with enough money to weather any storms |