Table 2.

Detailed roll-out plan 2017

# of LLINs Port of entry # of bales per port of entry # of cont. per port of entrya Planned date of arrival at port Planned date of distribution
Group 1
 Niassa 1,232,505 Nacala 24,650 56 January 2017 March 2017
 Cabo Delgado 1,138,866 22,777 52
Total Nacala 47,427 108
 Zambezia 3,193,976 Beira 63,880 145 March 2017
 Tete 1,588,423 31,768 72 April 2017
Total Beira 95,648 217
 Total group 1 7,153,770 143,075 325
Group 2
 Manica 1,196,811 Beira 23,936 54 April 2017 August 2017
 Sofala 1,254,615 25,092 57
Total Beira 49,029 111
 Inhambane 902,913 Maputo 18,058 41 September 2017
 Total group 2 3,354,339 67,087 152
Group 3
 Gaza 856,305 Maputo 17,126 39 June 2017 September 2017
 Maputo Province 1,084,182 21,684 49
 Maputo City 742,628 14,853 34
 Total group 3 2,683,115 53,662 122
Grand Total 13,191,224b 263,824 600

a Approximate number of containers (a container can accommodate 440 bales)

b Adding the 3,050,020 LLINs from Nampula province will get 16,241,244 LLINs