Table 4.

Fixed capital estimate for production of butanol from de-oiled rice bran.

A. Total plant direct cost (TPDC; physical cost) ($)
      Equipment purchase cost 32,385,000
      Installation 12,383,000
      Process piping 11,335,000
      Instrumentation 12,945,000
      Insulation 972,000
      Electrical 3,239,000
      Buildings 14,573,000
      Yard improvement 4,858,000
      Auxiliary facilities 12,954,000
      TPDC 105,652,000
B. Total plant indirect cost (TPIC)
      Engineering 26,413,000
      Construction 36,978,000
      TPIC 63,391,000
C. Total plant cost (TPC = TPDC + TPIC) 169,043,000
D. Contractor’s fee and contingency (CFC)
      Contractor’s fee 8,452,000
      Contingency 16,904,000
      CFC 25,357,000
E. Direct fixed capital cost (DFC = TPC + CFC) 194,400,000