Table 1.

Study schedule

Day 1
T0 Baseline T1 30 min after product application T2 2 h after product application T3 6 h after product application
Informed consent X
In‐/exclusion criteria X
Acclimatization X X X X
Application of test materials Xa
Visual evaluation X X X X

Instrumental measurements:

 Aquaflux

 Corneometer

 Raman

X X X X
a

First application under control of a trained technician.