Table 2.
The proportion of instruments placed on a tray, but not used during the procedure is a proxy indicator for work complexity and cost.
| The complexity of a prosthesis and instrumentation system is an important cost driver as well as a hidden source of failures within the scope of the instrument cycle | |||
|---|---|---|---|
| Criteria | Standard setting | Size-specific setting | Reduction in complexity (%) |
| Sample size | 14 | 18 | – |
| Number of instruments prepared | 156 | 91 | 42.67% |
| Proportion of instruments used | 32.67% | 54.64% | 40.21% |
| Number of trays | 6 | 3 | 50% |