Table 5.
Overview of the validation approach for the automated stores of the UZ KU Leuven Biobank.
| Phase (duration @ UZ KU Leuven Biobank) | Content | Who |
|---|---|---|
| Installation qualification (3 years) | Installation by manufacturer and Site Acceptance Test | Manufacturer in presence of user |
| Operational qualification (1 year) | Intended use: – Develop System Qualification and Acceptance Test – Time to place/pick 1–1000 samples – Time to freeze 1–100 samples – Scan performance of frozen and non-frozen tubes – Stress test by placing/picking >3,000 tubes – Universal Power Supply test during operation |
User |
| Labware verification: – Determine maximum fill volume and impact on system |
||
| Unintended use: – Create pick order for duplicate tube ID – Create pick order for tube absent from store – Insert labware with incorrect orientation |
||
| Cooling: – Determine Temperature homogeneity – Emergency power test and impact on cooling operations – City water backup test and impact on cooling operations |
||
| Alarm connection Test | ||
| Performance qualification (1 month) | Simulation of intended routine use of the equipment (2 week repeat of estimated sample submissions and requests) | User |
| Implementation | Routine operation, daily monitoring of PIR and PLR, use of SQAT before/after PM and planned interventions, SQAT after unplanned intervention | User |
PIR, Pick Retry Ratio; PLR, Place Retry Ratio; PM, Preventive maintenance; SQAT, System Qualification and Assessment Test.