Table 5.

Overview of the validation approach for the automated stores of the UZ KU Leuven Biobank.

Phase (duration @ UZ KU Leuven Biobank) Content Who
Installation qualification (3 years) Installation by manufacturer and Site Acceptance Test Manufacturer in presence of user
Operational qualification (1 year) Intended use:
– Develop System Qualification and Acceptance Test
– Time to place/pick 1–1000 samples
– Time to freeze 1–100 samples
– Scan performance of frozen and non-frozen tubes
– Stress test by placing/picking >3,000 tubes
– Universal Power Supply test during operation
User
Labware verification:
– Determine maximum fill volume and impact on system
Unintended use:
– Create pick order for duplicate tube ID
– Create pick order for tube absent from store
– Insert labware with incorrect orientation
Cooling:
– Determine Temperature homogeneity
– Emergency power test and impact on cooling operations
– City water backup test and impact on cooling operations
Alarm connection Test
Performance qualification (1 month) Simulation of intended routine use of the equipment (2 week repeat of estimated sample submissions and requests) User
Implementation Routine operation, daily monitoring of PIR and PLR, use of SQAT before/after PM and planned interventions, SQAT after unplanned intervention User

PIR, Pick Retry Ratio; PLR, Place Retry Ratio; PM, Preventive maintenance; SQAT, System Qualification and Assessment Test.