Table 2.

The component of chiller plant equipment for energy saving calculation in the case study.

Pre-retrofit stage Post-retrofit stage
Chiller plant Annual chiller energy use Annual chiller energy use
Annual chilled water pump energy use Annual chilled water pump energy use
Heat rejection Annual sea water pump energy use
Annual condensing water pump energy use
Annual energy use A = sum of the above B = sum of the above
Actual energy saving Energy savings = A−B (calculated based on the post-retrofit conditions)