Table 2.

Airflow exchange rate calculations by vault

Machine vault Measurement Airflow exchange per hour t99% (min) t99.9% (min)
Primary campus
Standard LINAC 1 Actual 10.07 27.72 41.14
Standard LINAC 2 Actual 5.94 46.53 69.97
Standard LINAC 3 Actual 5.83 47.39 71.30
Tomotherapy Actual 16.99 16.60 24.31
Specialty stereotactic Actual 7.63 36.40 54.39
Regional campus 1
All standard LINACs Minimum 12 23.34 34.49
Maximum 18 15.68 22.94
Tomotherapy Minimum 10 27.91 41.43
Maximum 15 18.75 27.55
All proton gantries Minimum 6 46.07 69.26
Maximum 12 23.34 34.49
Regional campus 2
Standard LINAC Actual 6.5 42.59 63.91
Regional campus 3
Standard LINAC Actual 8 34.74 51.86
Regional campus 4
Standard LINAC Actual 6.5 42.59 63.91

Abbreviations: LINAC = linear accelerator; t99% = time for 99% airflow exchange; t99.9% = time for full (99.9%) airflow exchange.

Actual measurements represent airflow measured under standard automatic temperature control and building automation systems settings. Minimum and maximum measurements represent the range of airflow rates delineated according room design specifications; these were not directly measured.