Table 5.
Overall Project Timeline
Study QUARTER | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
---|---|---|---|---|---|---|---|---|---|---|---|---|
Development Phase | ||||||||||||
IRB application | X | |||||||||||
Prepare practice materials | X | |||||||||||
Hire/train practice facilitators | X | X | ||||||||||
Assemble/update toolkits | X | X | X | X | X | X | X | X | X | X | X | X |
Intervention Phase (Dissemination and Implementation) | ||||||||||||
Region 1 activities | R | I | I | I | C | C | C | |||||
Region 2 activities | R | R | I | I | I | C | C | C | ||||
Region 3 activities | R | R | R | I | I | I | C | C | C | |||
Region 4 activities | R | R | R | R | I | I | I | C | C | C | ||
Region 5 activities | R | R | R | R | R | I | I | I | C | C | C | |
Data Collection and Analysis Phase | ||||||||||||
Regional data collection | X | X | X | X | X | X | X | X | X | X | ||
Midpoint and final analyses | X | X | X | X | ||||||||
Participation in evaluator and AHRQ collaborative activities | X | X | X | X | X | X | X | X | X | X | X | X |
Note: R practice recruitment, X scheduled activity